Complete remediation of the Overberg drug lab too complicated and too expensive: ‘The costs have already risen to 2.1 million euros’
The soil structure on the site turned out to be different from the initial investigations, says soil specialist Han de Rijk of the Utrecht Region Environmental Service: “We thought we…
Soil pollution around former drug lab Overberg much more serious than expected: ‘It is up to 7 meters deep’
The costs of the remediation were previously budgeted at more than 1 million euros, but are now likely to be much higher. Mayor Naafs said about this at the time:…
Local residents: slavery monument Griftpark stands in the way of soil remediation
Local residents of the Utrecht Griftpark emphasize once again that they want the slavery monument that will be placed in the park to be given a different place. An earlier…
Methanol, amphetamine and benzene: all of this is extracted from the ground during the remediation of mega drug lab Overberg
What exactly is in the ground around the drug lab? Eight different types of chemicals have been found in the soil and groundwater on the site of the former drug…
Remediation of mega drug lab at Overberg started after two years, size now really visible
Sjaak Vreeken is a crane operator at soil remediation company Sarpi Veolia. Since the beginning of this week, he has been working on the site with his excavator to prepare…
Hera and ACR create the first national operator in remediation and global service activities
(Finance) – The Group Hera, through the subsidiary Herambiente Servizi Industriali (HASI), today signed a binding agreement for a long-term partnership which provides for theacquisition of 60% of Reggiani Albertino’s…
Contractor found for remediation drug lab Overberg, cleaning job will start this fall
Because the convicted owner of the site is unable or unwilling to initiate the remediation itself, the municipality has now done so. That this took so long is because a…
Remediation of the former mega drug lab in Overberg will only start after the summer
OVERBERG – The remediation of the site around a former drug lab in Overberg will only start after the summer. The owner was given the chance to do it himself…