Council APPRES SENDING HUB PROPOSAL TO TEDER

Chatham-kent council has voted to take the next step with the community hub proposition, sending it to tender.

Content

Monday Night’s Meeting Took Place at the John D. Bradley Convention Center to Account The Public Interest, With a Large Gathering on Hand, as well as 17 DEPUTATIONS.

Council Voted 12-5 in Favour of Moving Ahead to the Construction Provides Process. However, Monday was not the final decision, as the bids still need to return to cover.

The $ 53 million Project Involves Moving the Civic Center, Library and Museum to the Form Sears Portion of the Downtown Chatham Center.

Architecturra Principal and Partner dan Amipone Said Needed Lifecycle Repair to the Existing Civic Center, Library and Museum Are Pegged at $ 47.8 million.

However, The Total Price for Renovations To All Three Rises To Just Over $ 108 million to meet standard for accessibility, Energy Efficiency, Modern Infrastructure and Public Service Delivery.

Content

The $ 53 million love is expected to decrease, with the Sale of Municipal Properties and the Money in Building Reserves, sincere Civic Center Upgrades WERE NOT COMPLETED – AT COUNCIL DIRECTION – IN PREVIOUS YEARS.

Last Month, Local Entrepreneur Rob Myers Announced He was putting up $ 5 million to establish the Myers Family Foundation to Benefit the proposed Library and Museum.

Mayor Darrin Canniff Credited the Civil Manner in Which Monday’s Meeting Took Place, as well as staff for their efforts on the project.

“The Countless Hours that they put in, and the love of pivots,” he said. “I’ve seen the up-hand the work you are Doing.”

If the Hub Project Ultimately Moves Ahead after Tendering, Construction Would Begin in December and continues for 18 to 24 months.

HUB PROPOSAL NEXT STEPS

June 2025: Construction initiate provides

September 2025: Council to consider award of general construction provides and consulting fees for contract administration

October 2025: Award Contract

December 2025: Begin Construction, with 18 to 24-Month Construction Period

End of 2027: Expected Completion Date

This story will be updated.